Land · Dunn County · T144N R96W

Section 11Township 144 North, Range 96 West

3 spacing units cover this section. The Industrial Commission signed 4 orders on them between 2007 and 2026, and 2 of those changed something.

At a glance

T144N R96WNorth ↑ · each square is one section (1 mile)123456789101112131415161718192021222324252627282930313233343536
  • 640-acre unit · section 11
  • 2,560-acre unit · sections 1, 2, 11 and 12
  • 2,560-acre unit · sections 2, 3, 10 and 11
Units overlap. Each was set up by a different order and has its own well allowance.
Spacing units over this section3640 and 2,560 acres
Orders on record42007 to 2026; 2 changed something, 2 restated the rules
Horizontal wells with laterals in that unit11 active; started 2006
Laterals that still fit4in 2 of the units; a count of space, not a plan

What happened on this land

The 640-acre unit first appears in the orders in 2007. 1 horizontal well has laterals in it, started in 2006.

  1. 2007
  2. Jan 16, 2007First on record

    First order on record for the 640-acre unit across section 11.

    Order 10888 · Case 9274 · Applicant: Kerr-McGee Oil & Gas Onshore LP

  3. 2015
  4. Jan 2, 2015Unit set up

    Set up the 2,560-acre unit over sections 1, 2, 11 and 12.

    Set up the 2,560-acre unit over sections 2, 3, 10 and 11.

    Order 24874 · Case 22540 · Applicant: XTO Energy Inc.

2 more orders restated the rules without changing them
  • Jan 2, 2015: Order 24942 (case 22607), Marathon Oil Co.
  • Sep 17, 2026: Order 35805 (case 32879), Phoenix Operating LLC

The units that cover it

A large unit can hold many more wells than its own order allows, because most of them belong to smaller units inside it. Oil totals overlap for the same reason.

640 acresSection 11

First order on record
Jan 2007 · Order 10888
Last real change
Jan 2007
Wells with laterals inside
1
Laterals that still fit
3
Pool
Murphy Creek-Bakken

2,560 acresSections 1, 2, 11 and 12

Set up
Jan 2015 · Order 24874
Last real change
Jan 2015
Wells with laterals inside
7
Laterals that still fit
1
Pool
Murphy Creek-Bakken

2,560 acresSections 2, 3, 10 and 11

Set up
Jan 2015 · Order 24874
Last real change
Jan 2015
Wells with laterals inside
4
Pool
Murphy Creek-Bakken

Wells in the 640-acre unit

Horizontal wells with at least 660 ft of lateral inside section 11, oldest first. Wells of any formation are listed.

Nearby

Sources and limits

Built November 12, 2026. Find another section · Cases & Orders · Methodology