The 1,284-acre unit was set up as a temporary spacing unit in 2012. A later order vacated the orders that set it up. 1 horizontal well has laterals in it, started in 2026.
2012
Jun 14, 2012Temporary unit
Set up a temporary spacing unit across sections 15 and 22 for a horizontal well.
Order 290-2012 · Docket 343-2012 · Applicant: Continental Resources, Inc · The Board's copy ↗
2025
Feb 20, 2025Temporary unit
Set up a temporary spacing unit across sections 3, 10, 15 and 22 for a horizontal well.
Order 27-2025 vacated the orders that set up the 1,284-acre unit.
Allowed up to 3 more horizontal wells in the 2,581-acre unit.
Order 28-2025 · Docket 54-2025 · Applicant: Kraken Oil & Gas LLC · The Board's copy ↗
The units that cover it
Montana lays new units over older ones, so one section can sit in several. Oil totals overlap for the same reason.
1,284 acresSections 15 and 22
An order ended this unit.
Drawn from the orders' land description; Montana has no spacing-unit map layer.
Temporary unit
Jun 2012 · Order 290-2012
Last real change
Feb 2025
Wells with laterals inside
1
Formation
Bakken/Three Forks
2,581 acresSections 3, 10, 15 and 22
Drawn from the orders' land description; Montana has no spacing-unit map layer.
Temporary unit
Feb 2025 · Order 27-2025
Orders allowing more wells
up to 3 more (2025)
Last real change
Feb 2025
Wells with laterals inside
1
Formation
Bakken/Three Forks
Wells in the 1,284-acre unit
Horizontal wells with at least 660 ft of lateral inside sections 15 and 22, oldest first. Wells of any formation are listed. A well's name opens it in the 3D viewer.
Thor 2756-3-22 #1HKraken Operating, LLC · Spudded · started 2026 · 10,264 ft of path inside · API 25-085-22101
Read by machine, not checked by a person. Order facts come from the orders of the Montana Board of Oil and Gas Conservation, as the Board posts them for each hearing, 2000 through the hearing of October 15, 2026. The signed order is the rule; each order links to the Board's own copy.
A record of orders, not title or current status. Nothing here says who owns anything, and a later order can change or end a unit.
Montana's steps. The Board sets up a temporary spacing unit for a first horizontal well, then a permanent unit once the well produces, and can pool the owners. A well-density order allows up to a stated number of wells more; the pages show each number as the order states it and do not add them up.
Bakken and Three Forks orders only, granted, and only where the order describes its land by section numbers. Orders that name the same sections make one unit. Orders from before 2000 are not on these pages yet.
Outlines are drawn from each order's land description on the federal section grid (BLM, fetched November 25, 2026); Montana has no spacing-unit map layer. A unit that crosses a township line is listed in each township it touches.
Wells come from the Board's well list (November 18, 2026): horizontal wells with at least 660 ft of the Board's simplified well path inside a unit, whatever formation they produce from. Oil is as reported in the Board's well-by-well production file, January 2003 to August 2026. Overlapping units count the same barrels. A well's status is the Board's word, not a judgement.
Not legal, engineering or investment advice. Corrections: see contact.