The 1,268-acre unit was set up as a temporary spacing unit in 2011. A later order vacated the orders that set it up. 4 horizontal wells have laterals in it.
2011
Dec 15, 2011Temporary unit
Set up a temporary spacing unit across sections 4 and 9 for a horizontal well.
Order 414-2011 · Docket 500-2011 · Applicant: Whiting Oil And Gas Corporation · The Board's copy ↗
2024
Oct 10, 2024Temporary unit
Set up a temporary spacing unit across section 4 for a horizontal well.
Order 126-2024 vacated the orders that set up the 1,268-acre unit.
Allowed up to 3 more horizontal wells in the 2,542-acre unit.
Order 161-2025 · Docket 231-2025 · Applicant: Kraken Oil & Gas LLC · The Board's copy ↗
The units that cover it
Montana lays new units over older ones, so one section can sit in several. Oil totals overlap for the same reason.
1,268 acresSections 4 and 9
An order ended this unit.
Drawn from the orders' land description; Montana has no spacing-unit map layer.
Temporary unit
Dec 2011 · Order 414-2011
Last real change
Oct 2024
Wells with laterals inside
4
Formation
Bakken/Three Forks
1,902 acresSection 4
An order ended this unit.
The unit also takes in sections 28, 33 of T26N R57E.
Drawn from the orders' land description; Montana has no spacing-unit map layer.
Temporary unit
Oct 2024 · Order 126-2024
Orders allowing more wells
up to 3 more (2024)
Last real change
Aug 2025
Wells with laterals inside
4
Formation
Bakken/Three Forks
2,542 acresSections 4 and 9
The unit also takes in sections 28, 33 of T26N R57E.
Drawn from the orders' land description; Montana has no spacing-unit map layer.
Temporary unit
Aug 2025 · Order 160-2025
Orders allowing more wells
up to 3 more (2025)
Last real change
Aug 2025
Wells with laterals inside
4
Formation
Bakken/Three Forks
Wells in the 1,268-acre unit
Horizontal wells with at least 660 ft of lateral inside sections 4 and 9, oldest first. Wells of any formation are listed. A well's name opens it in the 3D viewer.
Lincoln 28-33-4-9 #1HKraken Operating, LLC · Permit to Drill · 10,240 ft of path inside · API 25-083-23601
Lincoln 28-33-4-9 #4HKraken Operating, LLC · Permit to Drill · 10,210 ft of path inside · API 25-083-23604
Lincoln 28-33-4-9 #2HKraken Operating, LLC · Permit to Drill · 10,192 ft of path inside · API 25-083-23602
Lincoln 28-33-4-9 #3HKraken Operating, LLC · Permit to Drill · 10,181 ft of path inside · API 25-083-23603
Read by machine, not checked by a person. Order facts come from the orders of the Montana Board of Oil and Gas Conservation, as the Board posts them for each hearing, 2000 through the hearing of October 15, 2026. The signed order is the rule; each order links to the Board's own copy.
A record of orders, not title or current status. Nothing here says who owns anything, and a later order can change or end a unit.
Montana's steps. The Board sets up a temporary spacing unit for a first horizontal well, then a permanent unit once the well produces, and can pool the owners. A well-density order allows up to a stated number of wells more; the pages show each number as the order states it and do not add them up.
Bakken and Three Forks orders only, granted, and only where the order describes its land by section numbers. Orders that name the same sections make one unit. Orders from before 2000 are not on these pages yet.
Outlines are drawn from each order's land description on the federal section grid (BLM, fetched November 25, 2026); Montana has no spacing-unit map layer. A unit that crosses a township line is listed in each township it touches.
Wells come from the Board's well list (November 18, 2026): horizontal wells with at least 660 ft of the Board's simplified well path inside a unit, whatever formation they produce from. Oil is as reported in the Board's well-by-well production file, January 2003 to August 2026. Overlapping units count the same barrels. A well's status is the Board's word, not a judgement.
Not legal, engineering or investment advice. Corrections: see contact.