The 1,463-acre unit was set up as a temporary spacing unit in 2011, made a permanent unit in 2016 and pooled in 2016. An order in 2014 allowed more horizontal wells. 4 horizontal wells have laterals in it, started in 2014.
- 2011
- Dec 15, 2011Temporary unit
Set up a temporary spacing unit across part of sections 6, 7 and 18 for a horizontal well.
Order 454-2011 · Docket 156-2011 · Applicant: Abraxas Petroleum Corporation · The Board's copy ↗
- 2014
- May 1, 2014More wells allowed
Allowed more horizontal wells in the 1,463-acre unit.
Order 161-2014 · Docket 105-2014 · Applicant: Whiting Oil And Gas Corporation · The Board's copy ↗
- 2016
- Jun 16, 2016Permanent unit
Made the 1,463-acre unit a permanent spacing unit.
Order 19-2016 · Docket 19-2016 · Applicant: Whiting Oil And Gas Corporation · The Board's copy ↗
- Jun 16, 2016Pooled
Pooled the 1,463-acre unit: the owners' interests across it are combined, and all share in its wells.
Order 20-2016 · Docket 20-2016 · Applicant: Whiting Oil And Gas Corporation · The Board's copy ↗
- Jun 16, 2016Pooled
Pooled the 1,463-acre unit: the owners' interests across it are combined, and all share in its wells.
Order 21-2016 · Docket 21-2016 · Applicant: Whiting Oil And Gas Corporation · The Board's copy ↗
- Jun 16, 2016Pooled
Pooled the 1,463-acre unit: the owners' interests across it are combined, and all share in its wells.
Order 22-2016 · Docket 22-2016 · Applicant: Whiting Oil And Gas Corporation · The Board's copy ↗
- Jun 16, 2016Pooled
Pooled the 1,463-acre unit: the owners' interests across it are combined, and all share in its wells.
Order 23-2016 · Docket 23-2016 · Applicant: Whiting Oil And Gas Corporation · The Board's copy ↗
Wells in the 1,463-acre unit
Horizontal wells with at least 660 ft of lateral inside part of sections 6, 7 and 18, oldest first. Wells of any formation are listed. A well's name opens it in the 3D viewer.
- Malsam 14-18-3HWhiting Oil And Gas Corporation · Producing · started 2014 · 14,216 ft of path inside · API 25-083-23265
- Malsam 14-18-4HWhiting Oil And Gas Corporation · Producing · started 2014 · 13,488 ft of path inside · API 25-083-23266
- Malsam 14-18-2HWhiting Oil And Gas Corporation · Producing · started 2014 · 11,523 ft of path inside · API 25-083-23264
- Malsam 14-18-1HWhiting Oil And Gas Corporation · Producing · started 2014 · 11,368 ft of path inside · API 25-083-23263
Sources and limits
- Read by machine, not checked by a person. Order facts come from the orders of the Montana Board of Oil and Gas Conservation, as the Board posts them for each hearing, 2000 through the hearing of October 15, 2026. The signed order is the rule; each order links to the Board's own copy.
- A record of orders, not title or current status. Nothing here says who owns anything, and a later order can change or end a unit.
- Montana's steps. The Board sets up a temporary spacing unit for a first horizontal well, then a permanent unit once the well produces, and can pool the owners. A well-density order allows up to a stated number of wells more; the pages show each number as the order states it and do not add them up.
- Bakken and Three Forks orders only, granted, and only where the order describes its land by section numbers. Orders that name the same sections make one unit. Orders from before 2000 are not on these pages yet.
- Outlines are drawn from each order's land description on the federal section grid (BLM, fetched November 25, 2026); Montana has no spacing-unit map layer. A unit that crosses a township line is listed in each township it touches.
- Wells come from the Board's well list (November 18, 2026): horizontal wells with at least 660 ft of the Board's simplified well path inside a unit, whatever formation they produce from. Oil is as reported in the Board's well-by-well production file, January 2003 to August 2026. Overlapping units count the same barrels. A well's status is the Board's word, not a judgement.
- Not legal, engineering or investment advice. Corrections: see contact.
Built November 25, 2026. Find another section · The Bakken in Montana · Methodology