Land · Divide County · T163N R96W

Section 14Township 163 North, Range 96 West

One spacing unit covers this section. The Industrial Commission signed 3 orders on it between 2012 and 2025, and 2 of those changed something.

At a glance

T163N R96WNorth ↑ · each square is one section (1 mile)123456789101112131415161718192021222324252627282930313233343536
  • 1,280-acre unit · sections 14 and 23
The outline is the spacing unit that covers this section.
Spacing units over this section11,280 acres
Orders on record32012 to 2025; 2 changed something, 1 restated the rules
Most wells an order allows in the 1,280-acre unit1stated in 2012
Horizontal wells with laterals in that unit11 active; started 2011
Laterals that still fit3in this unit; a count of space, not a plan

What happened on this land

The 1,280-acre unit first appears in the orders in 2012, with 1 horizontal well allowed. 1 horizontal well has laterals in it, started in 2011.

12015202020251 wellMost horizontal wells an order has allowedWells started on the unit (one square each)
The 1,280-acre unit (sections 14 and 23). The line is the highest well count any order has stated so far: a ceiling, not wells drilled. Start dates are spud dates from the state's wells layer.
  1. 2012
  2. Oct 26, 2012First on record

    First order on record for the 1,280-acre unit across sections 14 and 23.

    Order 19476 · Case 17207 · Applicant: Samson Resources Co.

  3. Oct 26, 2012Well count set

    Allowed up to 1 horizontal well in the 1,280-acre unit.

    Order 20103 · Case 17834

1 more order restated the rules without changing them
  • Feb 14, 2025: Order 34024 (case 31324), Dakota Energy, L.L.C.

The unit that covers it

1,280 acresSections 14 and 23

First order on record
Oct 2012 · Order 19476
Most wells an order allows
1 · 2012
Last real change
Oct 2012
Wells with laterals inside
1
Laterals that still fit
3
Pool
Bounty School-Bakken

Wells in the 1,280-acre unit

Horizontal wells with at least 660 ft of lateral inside sections 14 and 23, oldest first. Wells of any formation are listed.