One spacing unit covers this section. The Industrial Commission signed 7 orders on it in 2026, and 1 of those changed something.
At a glance
2,560-acre unit · sections 13, 24, 25 and 36
The outline is the spacing unit that covers this section.
Spacing units over this section12,560 acres
Orders on record72026; 1 changed something, 6 restated the rules
Most wells an order allows in the 2,560-acre unit5stated in 2026
Laterals that still fit4in this unit; a count of space, not a plan
What happened on this land
The 2,560-acre unit first appears in the orders in 2026, with 5 horizontal wells allowed.
The 2,560-acre unit (sections 13, 24, 25 and 36). The line is the highest well count any order has stated so far: a ceiling, not wells drilled. Start dates are spud dates from the state's wells layer.
2026
May 28, 2026First on record
First order on record for the 2,560-acre unit across sections 13, 24, 25 and 36, with up to 5 horizontal wells allowed.
Order 35357 · Case 32518 · Applicant: Phoenix Operating LLC
6 more orders restated the rules without changing them
May 28, 2026: Order 35358 (case 32519)
May 28, 2026: Order 35359 (case 32520)
May 28, 2026: Order 35360 (case 32521)
May 28, 2026: Order 35466 (case 32620), Phoenix Operating LLC
Read by machine, not checked by a person. Order facts come from the signed orders of the North Dakota Industrial Commission, signed through October 21, 2026. The signed order is the rule.
A record of orders, not title or current status. Nothing here says who owns anything, and a later order can change or end a unit.
Well counts are what each order states. A later order can state a smaller number for something narrower, such as one more well. These pages show the highest count and the latest one read; neither is a statement of what is allowed today.
By section. A unit appears when the orders describe its land by section numbers in one township. Units described by lots or quarter sections may be missing, and a unit smaller than its sections covers only part of them.
Oil is as first reported in the free NDIC Monthly Production Reports, January 2003 to August 2026, for horizontal wells with at least 660 ft of lateral inside a unit, whatever formation they produce from. Overlapping units count the same barrels.
Units and wells come from the state's free GIS layers (spacing units of October 17, 2026, wells of November 1, 2026). A well's status is the Industrial Commission's code, not a judgement.
Not legal, engineering or investment advice. Corrections: see contact.