Land · Mountrail County · T157N R91W

Section 25Township 157 North, Range 91 West

2 spacing units cover this section. The Industrial Commission signed 11 orders on them between 2009 and 2026, and 8 of those changed something.

At a glance

T157N R91WNorth ↑ · each square is one section (1 mile)123456789101112131415161718192021222324252627282930313233343536
  • 1,280-acre unit · section 25
  • 2,560-acre unit · sections 24 and 25
Units overlap. Each was set up by a different order and has its own well allowance.
Spacing units over this section21,280 and 2,560 acres
Orders on record112009 to 2026; 8 changed something, 3 restated the rules
Most wells an order allows in the 1,280-acre unit4in 2012; the latest order read (2026) states 2
Horizontal wells with laterals in that unit22 active; started 2010 to 2011
Laterals that still fit3in 1 of the units; a count of space, not a plan

What happened on this land

The 1,280-acre unit first appears in the orders in 2010, with 1 horizontal well allowed. Orders in 2010 and 2012 raised that to 4. The latest order read, in 2026, states 2; a smaller number usually covers something narrower, not fewer wells for the unit. 2 horizontal wells have laterals in it, started between 2010 and 2011.

123420102015202020251 well4 wellsMost horizontal wells an order has allowedWells started on the unit (one square each)
The 1,280-acre unit (section 25). The line is the highest well count any order has stated so far: a ceiling, not wells drilled. Start dates are spud dates from the state's wells layer.
  1. 2009
  2. Aug 26, 2009Pooled

    Pooled the 1,280-acre unit: the owners' interests across it are combined, and all share in its wells.

    Order 13476 · Case 11372

  3. 2010
  4. Sep 3, 2010First on record

    First order on record for the 1,280-acre unit across section 25.

    Order 14677 · Case 12421 · Applicant: EOG Resources, Inc.

  5. Sep 3, 2010Well count set

    Allowed up to 1 horizontal well in the 1,280-acre unit.

    Order 14795 · Case 12538 · Applicant: EOG Resources, Inc.

  6. Dec 8, 2010More wells allowed

    Raised the 1,280-acre unit from 1 to 3 horizontal wells allowed.

    Order 15683 · Case 13407 · Applicant: Hess Corp.

  7. 2011
  8. Mar 23, 2011Pooled

    Pooled the 1,280-acre unit: the owners' interests across it are combined, and all share in its wells.

    Order 16441 · Case 14166 · Applicant: EOG Resources, Inc.

  9. 2012
  10. Feb 2, 2012More wells allowed

    Raised the 1,280-acre unit from 3 to 4 horizontal wells allowed.

    Order 17855 · Case 15609 · Applicant: Slawson Exploration Co., Inc.

  11. 2026
  12. Jun 3, 2026Unit set up

    Set up the 2,560-acre unit across sections 24 and 25, with up to 1 horizontal well allowed.

    States up to 2 horizontal wells for the 1,280-acre unit; an earlier order stated up to 4.

    Order 35556 · Case 32699 · Applicant: EOG Resources, Inc.

  13. Sep 29, 2026Pooled

    Pooled the 2,560-acre unit: the owners' interests across it are combined, and all share in its wells.

    Order 36143 · Case 33133 · Applicant: EOG Resources, Inc.

3 more orders restated the rules without changing them
  • Sep 3, 2010: Order 15043 (case 12780), Hunt Oil Co.
  • Dec 8, 2010: Order 15969 (case 13691), EOG Resources, Inc.
  • Feb 2, 2012: Order 18711 (case 16445), EOG Resources, Inc.

The units that cover it

A large unit can hold many more wells than its own order allows, because most of them belong to smaller units inside it. Oil totals overlap for the same reason.

1,280 acresSection 25

First order on record
Sep 2010 · Order 14677
Most wells an order allows
4 · 2012
Latest count read
2 · 2026
Last real change
Jun 2026
Wells with laterals inside
2
Laterals that still fit
3
Pools
Clear Water-Bakken, Ross-Bakken

2,560 acresSections 24 and 25

Set up
Jun 2026 · Order 35556
Most wells an order allows
1 · 2026
Last real change
Sep 2026
Wells with laterals inside
4
Pool
Clear Water-Bakken

Wells in the 1,280-acre unit

Horizontal wells with at least 660 ft of lateral inside section 25, oldest first. Wells of any formation are listed.

Nearby

Sources and limits

Built November 12, 2026. Find another section · Cases & Orders · Methodology