One spacing unit covers this section. The Industrial Commission signed 7 orders on it between 2012 and 2026, and 2 of those changed something.
At a glance
944-acre unit · part of sections 10 and 11
The outline is the spacing unit that covers this section.
Spacing units over this section1944 acres
Orders on record72012 to 2026; 2 changed something, 5 restated the rules
Most wells an order allows in the 944-acre unit1stated in 2023
What happened on this land
The 944-acre unit first appears in the orders in 2023, with 1 horizontal well allowed.
The 944-acre unit (part of sections 10 and 11). The line is the highest well count any order has stated so far: a ceiling, not wells drilled. Start dates are spud dates from the state's wells layer.
2012
Jul 19, 2012Pooled
Pooled the 944-acre unit: the owners' interests across it are combined, and all share in its wells.
Order 19939 · Case 17669
2023
Jan 3, 2023First on record
First order on record for the 944-acre unit across part of sections 10 and 11, with up to 1 horizontal well allowed.
Order 32131 · Case 29561
5 more orders restated the rules without changing them
Jan 3, 2023: Order 32132 (case 29562)
Jan 3, 2023: Order 32133 (case 29563)
Jan 3, 2023: Order 32134 (case 29564)
Dec 6, 2023: Order 32567 (case 29959)
Aug 6, 2026: Order 34752 (case 31999)
The unit that covers it
944 acresPart of sections 10 and 11
From the orders only; not in the state's current unit layer.
Read by machine, not checked by a person. Order facts come from the signed orders of the North Dakota Industrial Commission, signed through October 21, 2026. The signed order is the rule.
A record of orders, not title or current status. Nothing here says who owns anything, and a later order can change or end a unit.
Well counts are what each order states. A later order can state a smaller number for something narrower, such as one more well. These pages show the highest count and the latest one read; neither is a statement of what is allowed today.
By section. A unit appears when the orders describe its land by section numbers in one township. Units described by lots or quarter sections may be missing, and a unit smaller than its sections covers only part of them.
Oil is as first reported in the free NDIC Monthly Production Reports, January 2003 to August 2026, for horizontal wells with at least 660 ft of lateral inside a unit, whatever formation they produce from. Overlapping units count the same barrels.
Units and wells come from the state's free GIS layers (spacing units of October 17, 2026, wells of November 1, 2026). A well's status is the Industrial Commission's code, not a judgement.
Not legal, engineering or investment advice. Corrections: see contact.