Land · Williams County · T155N R96W

Section 13Township 155 North, Range 96 West

2 spacing units cover this section. The Industrial Commission signed 17 orders on them between 2007 and 2025, and 10 of those changed something.

At a glance

T155N R96WNorth ↑ · each square is one section (1 mile)123456789101112131415161718192021222324252627282930313233343536
  • 1,280-acre unit · part of sections 13, 14, 23 and 24
  • 2,560-acre unit · sections 12 and 13
Units overlap. Each was set up by a different order and has its own well allowance.
Spacing units over this section21,280 and 2,560 acres
Orders on record172007 to 2025; 10 changed something, 7 restated the rules
Horizontal wells with laterals in that unit1612 active; started 2006 to 2020

What happened on this land

The 1,280-acre unit first appears in the orders in 2015. 16 horizontal wells have laterals in it, started between 2006 and 2020.

  1. 2007
  2. Apr 17, 2007First on record

    First order on record for the 2,560-acre unit across sections 12 and 13.

    Order 11060 · Case 9393

  3. Oct 26, 2007Pooled

    Pooled the 2,560-acre unit: the owners' interests across it are combined, and all share in its wells.

    Order 11411 · Case 9699 · Applicant: Hess Corp.

  4. 2011
  5. Jul 29, 2011Well count set

    Allowed up to 3 horizontal wells in the 2,560-acre unit.

    Order 16828 · Case 14550 · Applicant: Continental Resources, Inc.

  6. 2012
  7. Jun 21, 2012Pooled

    Pooled the 2,560-acre unit: the owners' interests across it are combined, and all share in its wells.

    Order 19770 · Case 17500 · Applicant: Hess Corp.

  8. 2013
  9. Apr 3, 2013More wells allowed

    Raised the 2,560-acre unit from 3 to 5 horizontal wells allowed.

    Order 20611 · Case 18342 · Applicant: XTO Energy Inc.

  10. 2015
  11. Apr 7, 2015First on record

    First order on record for the 1,280-acre unit across part of sections 13, 14, 23 and 24.

    Order 23585 · Case 21281 · Applicant: XTO Energy Inc.

  12. Nov 20, 2015Pooled

    Pooled the 1,280-acre unit: the owners' interests across it are combined, and all share in its wells.

    Order 26979 · Case 24615 · Applicant: Hess Bakken Investments II, LLC,

  13. 2016
  14. Aug 15, 2016More wells allowed

    Raised the 2,560-acre unit from 5 to 6 horizontal wells allowed.

    Order 27531 · Case 25124 · Applicant: Hess Bakken Investments II, LLC

  15. Aug 19, 2016Pooled

    Pooled the 2,560-acre unit: the owners' interests across it are combined, and all share in its wells.

    Order 27538 · Case 25131 · Applicant: Hess Bakken Investments II, LLC,

  16. 2019
  17. Aug 21, 2019More wells allowed

    Raised the 2,560-acre unit from 6 to 7 horizontal wells allowed.

    Order 29806 · Case 27362 · Applicant: Hess Bakken Investments II, LLC

7 more orders restated the rules without changing them
  • Mar 30, 2011: Order 15670 (case 13394), Murex Petroleum Corp.
  • Jul 29, 2011: Order 17172 (case 14922), Hess Corp.
  • Apr 3, 2013: Order 20929 (case 18627), Hess Corp.
  • Apr 7, 2015: Order 24790 (case 22456), Hess Bakken Investments II, LLC
  • Oct 13, 2016: Order 27650 (case 25231), Liberty Resources Management Company, LLC
  • Aug 21, 2019: Order 29814 (case 27370), Hess Bakken Investments II, LLC
  • Nov 5, 2025: Order 34618 (case 31876), Continental Resources, Inc.

The units that cover it

A large unit can hold many more wells than its own order allows, because most of them belong to smaller units inside it. Oil totals overlap for the same reason.

1,280 acresPart of sections 13, 14, 23 and 24

First order on record
Apr 2015 · Order 23585
Last real change
Nov 2015
Wells with laterals inside
16
Pool
Beaver Lodge-Bakken

2,560 acresSections 12 and 13

First order on record
Apr 2007 · Order 11060
Most wells an order allows
7 · 2019
Last real change
Aug 2019
Wells with laterals inside
32
Oil reported
2,061,532 bbl
Pool
Beaver Lodge-Bakken

Wells in the 1,280-acre unit

Horizontal wells with at least 660 ft of lateral inside part of sections 13, 14, 23 and 24, oldest first. Wells of any formation are listed.

Nearby

Sources and limits

Built November 12, 2026. Find another section · Cases & Orders · Methodology