Land · Williams County · T153N R104W

Section 15Township 153 North, Range 104 West

One spacing unit covers this section. The Industrial Commission signed 3 orders on it between 2010 and 2026, and 2 of those changed something.

At a glance

T153N R104WNorth ↑ · each square is one section (1 mile)123456789101112131415161718192021222324252627282930313233343536
  • 960-acre unit · part of sections 10, 11, 14 and 15
The outline is the spacing unit that covers this section.
Spacing units over this section1960 acres
Orders on record32010 to 2026; 2 changed something, 1 restated the rules
Most wells an order allows in the 960-acre unit1stated in 2010
Horizontal wells with laterals in that unit10 active; started 2012
Laterals that still fit2in this unit; a count of space, not a plan

What happened on this land

The 960-acre unit was set up in 2010, with 1 horizontal well allowed. 1 horizontal well has laterals in it, started in 2012.

120102015202020251 wellMost horizontal wells an order has allowedWells started on the unit (one square each)
The 960-acre unit (part of sections 10, 11, 14 and 15). The line is the highest well count any order has stated so far: a ceiling, not wells drilled. Start dates are spud dates from the state's wells layer.
  1. 2010
  2. Aug 5, 2010Unit set up

    Set up the 960-acre unit across part of sections 10, 11, 14 and 15, with up to 1 horizontal well allowed.

    Order 14802 · Case 12545 · Applicant: Zenergy, Inc.

  3. 2011
  4. Dec 14, 2011Pooled

    Pooled the 960-acre unit: the owners' interests across it are combined, and all share in its wells.

    Order 18065 · Case 15810 · Applicant: EOG Resources, Inc.

1 more order restated the rules without changing them
  • Sep 11, 2026: Order 35950 (case 33000), Oasis Petroleum North America LLC

The unit that covers it

960 acresPart of sections 10, 11, 14 and 15

Set up
Aug 2010 · Order 14802
Most wells an order allows
1 · 2010
Last real change
Dec 2011
Wells with laterals inside
1
Laterals that still fit
2
Pool
Painted Woods-Bakken

Wells in the 960-acre unit

Horizontal wells with at least 660 ft of lateral inside part of sections 10, 11, 14 and 15, oldest first. Wells of any formation are listed.

Nearby

Sources and limits

Built November 12, 2026. Find another section · Cases & Orders · Methodology