Land · McKenzie County · T152N R96W

Section 31Township 152 North, Range 96 West

3 spacing units cover this section. The Industrial Commission signed 16 orders on them between 2011 and 2024, and 8 of those changed something. Wells in the smallest unit have reported 2.7 million barrels of oil.

At a glance

T152N R96WNorth ↑ · each square is one section (1 mile)123456789101112131415161718192021222324252627282930313233343536
  • 640-acre unit · section 31
  • 1,280-acre unit · sections 30 and 31
  • 2,560-acre unit · sections 29, 30, 31 and 32
Units overlap. Each was set up by a different order and has its own well allowance.
Spacing units over this section3640, 1,280 and 2,560 acres
Orders on record162011 to 2024; 8 changed something, 8 restated the rules
Horizontal wells with laterals in that unit1111 active; started 2010 to 2021
Oil those wells have reported2,664,776barrels, Jan 2003 to Aug 2026

What happened on this land

11 horizontal wells have laterals in it, started between 2010 and 2021.

  1. 2011
  2. May 18, 2011Pooled

    Pooled the 640-acre unit: the owners' interests across it are combined, and all share in its wells.

    Order 16913 · Case 14635 · Applicant: Newfield Production Co.

  3. 2012
  4. May 30, 2012First on record

    First order on record for the 1,280-acre unit across sections 30 and 31, with up to 6 horizontal wells allowed.

    Order 18840 · Case 16574 · Applicant: Newfield Production Co.

  5. 2014
  6. Jun 16, 2014First on record

    First order on record for the 2,560-acre unit across sections 29, 30, 31 and 32.

    Order 23653 · Case 21349 · Applicant: Newfield Production Co.

  7. Jun 16, 2014Well count set

    Allowed up to 1 horizontal well in the 2,560-acre unit.

    Order 24509 · Case 22175 · Applicant: Newfield Production Co.

  8. Aug 29, 2014Pooled

    Pooled the 2,560-acre unit: the owners' interests across it are combined, and all share in its wells.

    Order 24895 · Case 22561 · Applicant: Newfield Production Co.

  9. Sep 19, 2014Pooled

    Pooled the 1,280-acre unit: the owners' interests across it are combined, and all share in its wells.

    Order 22851 · Case 20545 · Applicant: Newfield Production Co.

  10. 2021
  11. Feb 9, 2021More wells allowed

    Raised the 1,280-acre unit from 6 to 12 horizontal wells allowed.

    Raised the 2,560-acre unit from 1 to 2 horizontal wells allowed.

    Order 31199 · Case 28656 · Applicant: Ovintiv Production Inc.

  12. Sep 2, 2021Well count set

    Allowed up to 2 lease-line wells in the 2,560-acre unit, running north–south.

    Restated the rules for the 1,280-acre unit (12 wells).

    Order 31486 · Case 28937

8 more orders restated the rules without changing them
  • May 30, 2012: Order 19037 (case 16768), Newfield Production Co
  • Nov 5, 2020: Order 31112 (case 28569), Burlington Resources Oil & Gas Co. LP
  • Feb 9, 2021: Order 31200 (case 28657), Ovintiv Production Inc.
  • Jan 11, 2022: Order 31532 (case 28981)
  • Apr 25, 2022: Order 31818 (case 29249)
  • Jul 29, 2022: Order 31992 (case 29421)
  • Mar 17, 2023: Order 32323 (case 29716)
  • Jan 10, 2024: Order 33063 (case 30450), Grayson Mill Operating, LLC

The units that cover it

A large unit can hold many more wells than its own order allows, because most of them belong to smaller units inside it. Oil totals overlap for the same reason.

640 acresSection 31

Last real change
May 2011
Wells with laterals inside
11
Oil reported
2,664,776 bbl
Pool
Westberg-Bakken

1,280 acresSections 30 and 31

First order on record
May 2012 · Order 18840
Most wells an order allows
12 · 2021
Last real change
Feb 2021
Wells with laterals inside
12
Oil reported
2,775,946 bbl
Pool
Westberg-Bakken

2,560 acresSections 29, 30, 31 and 32

First order on record
Jun 2014 · Order 23653
Most wells an order allows
2 · 2021
Lease-line wells
2
Last real change
Sep 2021
Wells with laterals inside
28
Oil reported
6,178,118 bbl
Pool
Westberg-Bakken

Wells in the 640-acre unit

Horizontal wells with at least 660 ft of lateral inside section 31, oldest first. Wells of any formation are listed.

Nearby

Sources and limits

Built November 12, 2026. Find another section · Cases & Orders · Methodology