2 spacing units cover this section. The Industrial Commission signed 13 orders on them between 2010 and 2026, and 8 of those changed something.

At a glance

T152N R102WNorth ↑ · each square is one section (1 mile)123456789101112131415161718192021222324252627282930313233343536
  • 2,560-acre unit · sections 1, 2, 11 and 12
  • 2,560-acre unit · sections 1 and 12
Units overlap. Each was set up by a different order and has its own well allowance.
Spacing units over this section22,560 acres
Orders on record132010 to 2026; 8 changed something, 5 restated the rules
Most wells an order allows in the 2,560-acre unit over sections 1, 2, 11 and 122stated in 2018
Horizontal wells with laterals in that unit75 active; started 2010 to 2024
Laterals that still fit6in 1 of the units; a count of space, not a plan

What happened on this land

The 2,560-acre unit over sections 1, 2, 11 and 12 was set up in 2018, with 2 horizontal wells allowed. 7 horizontal wells have laterals in it, started between 2010 and 2024.

1220102015202020252 wellsMost horizontal wells an order has allowedWells started on the unit (one square each)
The 2,560-acre unit over sections 1, 2, 11 and 12 (sections 1, 2, 11 and 12). The line is the highest well count any order has stated so far: a ceiling, not wells drilled. Start dates are spud dates from the state's wells layer.
  1. 2010
  2. Jan 15, 2010Unit set up

    Set up the 2,560-acre unit over sections 1 and 12.

    Order 14073 · Case 11886 · Applicant: Encore Operating, L.P.

  3. 2011
  4. Oct 19, 2011Well count set

    Allowed up to 1 horizontal well in the 2,560-acre unit over sections 1 and 12.

    Order 17301 · Case 15050 · Applicant: Denbury Onshore, LLC

  5. 2012
  6. Feb 10, 2012Pooled

    Pooled the 2,560-acre unit over sections 1 and 12: the owners' interests across it are combined, and all share in its wells.

    Order 17345 · Case 15094 · Applicant: Denbury Onshore, LLC

  7. 2013
  8. Feb 7, 2013More wells allowed

    Raised the 2,560-acre unit over sections 1 and 12 from 1 to 7 horizontal wells allowed.

    Order 18255 · Case 15992 · Applicant: Denbury Onshore, LLC

  9. 2015
  10. Sep 3, 2015Well count stated

    States up to 2 horizontal wells for the 2,560-acre unit over sections 1 and 12; an earlier order stated up to 7.

    Order 25331 · Case 22998

  11. 2018
  12. Jan 3, 2018Unit set up

    Set up the 2,560-acre unit over sections 1, 2, 11 and 12, with up to 2 horizontal wells allowed.

    Order 28587 · Case 26171 · Applicant: Oasis Petroleum North America LLC

  13. 2023
  14. Apr 25, 2023More wells allowed

    Raised the 2,560-acre unit over sections 1 and 12 from 7 to 12 horizontal wells allowed.

    Order 32506 · Case 29901

  15. 2025
  16. Oct 9, 2025Well count stated

    States up to 2 horizontal wells for the 2,560-acre unit over sections 1 and 12; an earlier order stated up to 12.

    Order 34743 · Case 31990 · Applicant: Oasis Petroleum North America LLC

5 more orders restated the rules without changing them
  • Oct 19, 2011: Order 17746 (case 15500)
  • Jun 1, 2012: Order 19058 (case 16789), XTO Energy Inc.
  • Jan 20, 2015: Order 25454 (case 23125), SM Energy Co.
  • Sep 3, 2015: Order 26145 (case 23804), XTO Energy Inc.
  • Mar 30, 2026: Order 34967 (case 32212)

The units that cover it

A large unit can hold many more wells than its own order allows, because most of them belong to smaller units inside it. Oil totals overlap for the same reason.

2,560 acresSections 1, 2, 11 and 12

Set up
Jan 2018 · Order 28587
Most wells an order allows
2 · 2018
Last real change
Jan 2018
Wells with laterals inside
7
Pool
Indian Hill-Bakken

2,560 acresSections 1 and 12

Set up
Jan 2010 · Order 14073
Most wells an order allows
12 · 2023
Latest count read
2 · 2026
Last real change
Oct 2025
Wells with laterals inside
9
Oil reported
241,736 bbl
Laterals that still fit
6
Pool
Indian Hill-Bakken

Wells in the 2,560-acre unit over sections 1, 2, 11 and 12

Horizontal wells with at least 660 ft of lateral inside sections 1, 2, 11 and 12, oldest first. Wells of any formation are listed.

Nearby

Sources and limits

Built November 12, 2026. Find another section · Cases & Orders · Methodology