Land · McKenzie County · T151N R98W

Section 13Township 151 North, Range 98 West

2 spacing units cover this section. The Industrial Commission signed 11 orders on them between 2008 and 2025, and 7 of those changed something.

At a glance

T151N R98WNorth ↑ · each square is one section (1 mile)123456789101112131415161718192021222324252627282930313233343536
  • 2,560-acre unit · sections 13, 14, 23 and 24
  • 2,560-acre unit · sections 13 and 24
Units overlap. Each was set up by a different order and has its own well allowance.
Spacing units over this section22,560 acres
Orders on record112008 to 2025; 7 changed something, 4 restated the rules
Most wells an order allows in the 2,560-acre unit over sections 13, 14, 23 and 241stated in 2014
Horizontal wells with laterals in that unit1615 active; started 2011 to 2023
Laterals that still fit5in 1 of the units; a count of space, not a plan

What happened on this land

The 2,560-acre unit over sections 13, 14, 23 and 24 was set up in 2014, with 1 horizontal well allowed. 16 horizontal wells have laterals in it, started between 2011 and 2023.

12015202020251 wellMost horizontal wells an order has allowedWells started on the unit (one square each)
The 2,560-acre unit over sections 13, 14, 23 and 24 (sections 13, 14, 23 and 24). The line is the highest well count any order has stated so far: a ceiling, not wells drilled. Start dates are spud dates from the state's wells layer.
  1. 2008
  2. Oct 24, 2008First on record

    First order on record for the 2,560-acre unit over sections 13 and 24.

    Order 12378 · Case 10475 · Applicant: ST. Mary Land & Expl. Co.

  3. 2011
  4. Jan 10, 2011Pooled

    Pooled the 2,560-acre unit over sections 13 and 24: the owners' interests across it are combined, and all share in its wells.

    Order 16152 · Case 13868 · Applicant: Encore Operating L.P.

  5. 2012
  6. Mar 7, 2012Well count set

    Allowed up to 7 horizontal wells in the 2,560-acre unit over sections 13 and 24.

    Order 18104 · Case 15849 · Applicant: Denbury Onshore, LLC

  7. 2013
  8. Oct 4, 2013More wells allowed

    Raised the 2,560-acre unit over sections 13 and 24 from 7 to 10 horizontal wells allowed.

    Order 21900 · Case 19594 · Applicant: SM Energy Co.

  9. 2014
  10. Feb 12, 2014Unit set up

    Set up the 2,560-acre unit over sections 13, 14, 23 and 24, with up to 1 horizontal well allowed.

    Order 23464 · Case 21160 · Applicant: XTO Energy Inc.

  11. 2015
  12. Feb 18, 2015Well count stated

    States up to 2 horizontal wells for the 2,560-acre unit over sections 13 and 24; an earlier order stated up to 10.

    Order 25774 · Case 23434 · Applicant: XTO Energy Inc.

  13. 2024
  14. Nov 1, 2024Pooled

    Pooled the 2,560-acre unit over sections 13 and 24: the owners' interests across it are combined, and all share in its wells.

    Order 33510 · Case 30856 · Applicant: Continental Resources, Inc.

4 more orders restated the rules without changing them
  • Aug 1, 2011: Order 17062 (case 14786), Newfield Production Co.
  • Oct 4, 2013: Order 23012 (case 20707), XTO Energy Inc.
  • Dec 16, 2015: Order 23712 (case 21381), Continental Resources, Inc.
  • Oct 17, 2025: Order 34449 (case 31713), Devon Energy Williston, LLC

The units that cover it

A large unit can hold many more wells than its own order allows, because most of them belong to smaller units inside it. Oil totals overlap for the same reason.

2,560 acresSections 13, 14, 23 and 24

Set up
Feb 2014 · Order 23464
Most wells an order allows
1 · 2014
Last real change
Feb 2014
Wells with laterals inside
16
Pool
Siverston-Bakken

2,560 acresSections 13 and 24

First order on record
Oct 2008 · Order 12378
Most wells an order allows
10 · 2013
Latest count read
2 · 2015
Last real change
Nov 2024
Wells with laterals inside
17
Oil reported
1,738,405 bbl
Laterals that still fit
5
Pools
Elidah-Bakken, Siverston-Bakken

Wells in the 2,560-acre unit over sections 13, 14, 23 and 24

Horizontal wells with at least 660 ft of lateral inside sections 13, 14, 23 and 24, oldest first. Wells of any formation are listed.

Nearby

Sources and limits

Built November 12, 2026. Find another section · Cases & Orders · Methodology