Land · McLean County · T150N R91W

Section 1Township 150 North, Range 91 West

2 spacing units cover this section. The Industrial Commission signed 15 orders on them between 2014 and 2026, and 2 of those changed something.

At a glance

T150N R91WNorth ↑ · each square is one section (1 mile)123456789101112131415161718192021222324252627282930313233343536
  • 1,920-acre unit · sections 1, 2 and 3
  • 1,920-acre unit · part of sections 1, 2, 3, 10, 11 and 12
Units overlap. Each was set up by a different order and has its own well allowance.
Spacing units over this section21,920 acres
Orders on record152014 to 2026; 2 changed something, 13 restated the rules
Most wells an order allows in the 1,920-acre unit over sections 1, 2 and 324up from 8 in 2014
Laterals that still fit10in these units; a count of space, not a plan

What happened on this land

The 1,920-acre unit over sections 1, 2 and 3 was set up in 2014, with 8 horizontal wells allowed. An order in 2017 raised that to 24.

61218242015202020258 wells24 wellsMost horizontal wells an order has allowed
The 1,920-acre unit over sections 1, 2 and 3 (sections 1, 2 and 3). The line is the highest well count any order has stated so far: a ceiling, not wells drilled. Start dates are spud dates from the state's wells layer.
  1. 2014
  2. Jul 15, 2014Unit set up

    Set up the 1,920-acre unit over sections 1, 2 and 3, with up to 8 horizontal wells allowed.

    Order 24007 · Case 21653 · Applicant: SHD Oil & Gas, LLC

  3. 2017
  4. Jun 22, 2017First on record

    First order on record for the 1,920-acre unit over sections 1, 2, 3, 10, 11 and 12, with up to 3 horizontal wells allowed.

    Raised the 1,920-acre unit over sections 1, 2 and 3 from 8 to 24 horizontal wells allowed.

    Order 25441 · Case 23112 · Applicant: QEP Energy Co.

13 more orders restated the rules without changing them
  • May 11, 2016: Order 25585 (case 23242), Marathon Oil Co.
  • Jun 22, 2017: Order 26416 (case 24073), QEP Energy Co.
  • Jun 22, 2017: Order 26748 (case 24381), QEP Energy Co.
  • Jun 22, 2017: Order 26779 (case 24412), SHD Oil & Gas, LLC
  • Jun 22, 2017: Order 26780 (case 24413), SHD Oil & Gas, LLC
  • Jun 22, 2017: Order 26923 (case 24557), SHD Oil & Gas, LLC
  • Nov 9, 2017: Order 28168 (case 25757), SHD Oil & Gas, LLC
  • Jan 22, 2021: Order 31177 (case 28635), SHD Oil & Gas, LLC
  • Jul 8, 2021: Order 31265 (case 28720), EOG Resources, Inc.
  • Mar 25, 2022: Order 31718 (case 29151), Oasis Petroleum North America LLC
  • Oct 27, 2025: Order 34057 (case 31357), Spotted Hawk Development, LLC
  • Feb 24, 2026: Order 35255 (case 32475), Oasis Petroleum North America LLC
  • Feb 24, 2026: Order 35256 (case 32476), Oasis Petroleum North America LLC

The units that cover it

A large unit can hold many more wells than its own order allows, because most of them belong to smaller units inside it. Oil totals overlap for the same reason.

1,920 acresSections 1, 2 and 3

Set up
Jul 2014 · Order 24007
Most wells an order allows
24 · 2017
Last real change
Jun 2017
Wells with laterals inside
0
Laterals that still fit
8
Pool
Deep Water Creek Bay-Bakken

1,920 acresPart of sections 1, 2, 3, 10, 11 and 12

First order on record
Jun 2017 · Order 25441
Most wells an order allows
3 · 2017
Last real change
Jun 2017
Wells with laterals inside
2
Laterals that still fit
2
Pool
Deep Water Creek Bay-Bakken

Nearby

Sources and limits

Built November 12, 2026. Find another section · Cases & Orders · Methodology