3 spacing units cover this section. The Industrial Commission signed 9 orders on them between 2010 and 2026, and 6 of those changed something.

At a glance

T150N R104WNorth ↑ · each square is one section (1 mile)123456789101112131415161718192021222324252627282930313233343536
  • 1,280-acre unit · part of sections 2, 3, 10 and 11
  • 1,280-acre unit · part of sections 3, 4, 9 and 10
  • 1,280-acre unit · sections 3 and 10
Units overlap. Each was set up by a different order and has its own well allowance.
Spacing units over this section31,280 acres
Orders on record92010 to 2026; 6 changed something, 3 restated the rules
Most wells an order allows in the 1,280-acre unit over sections 2, 3, 10 and 111stated in 2013
Horizontal wells with laterals in that unit64 active; started 2012 to 2014
Laterals that still fit1in 1 of the units; a count of space, not a plan

What happened on this land

The 1,280-acre unit over sections 2, 3, 10 and 11 was set up in 2013, with 1 horizontal well allowed. 6 horizontal wells have laterals in it, started between 2012 and 2014.

12015202020251 wellMost horizontal wells an order has allowedWells started on the unit (one square each)
The 1,280-acre unit over sections 2, 3, 10 and 11 (part of sections 2, 3, 10 and 11). The line is the highest well count any order has stated so far: a ceiling, not wells drilled. Start dates are spud dates from the state's wells layer.
  1. 2010
  2. Dec 21, 2010Unit set up

    Set up the 1,280-acre unit over sections 3 and 10, with up to 1 horizontal well allowed.

    Order 15467 · Case 13194 · Applicant: Petro-Hunt, L.L.C.

  3. 2013
  4. Feb 1, 2013More wells allowed

    Raised the 1,280-acre unit over sections 3 and 10 from 1 to 5 horizontal wells allowed.

    Order 21096 · Case 18794 · Applicant: Petro-Hunt, LLC

  5. Jun 6, 2013Pooled

    Pooled the 1,280-acre unit over sections 3 and 10: the owners' interests across it are combined, and all share in its wells.

    Order 22357 · Case 20052 · Applicant: Petro-Hunt, L.L.C.

  6. Sep 6, 2013Unit set up

    Set up the 1,280-acre unit over sections 2, 3, 10 and 11, with up to 1 horizontal well allowed.

    Set up the 1,280-acre unit over sections 3, 4, 9 and 10, with up to 1 horizontal well allowed.

    Order 22722 · Case 20416 · Applicant: Whiting Oil And Gas Corp.

  7. 2018
  8. Nov 5, 2018Pooled

    Pooled the 1,280-acre unit over sections 2, 3, 10 and 11: the owners' interests across it are combined, and all share in its wells.

    Order 29430 · Case 26985 · Applicant: Whiting Oil And Gas Corp.

  9. Nov 5, 2018Pooled

    Pooled the 1,280-acre unit over sections 3, 4, 9 and 10: the owners' interests across it are combined, and all share in its wells.

    Order 29431 · Case 26986 · Applicant: Whiting Oil And Gas Corp.

3 more orders restated the rules without changing them
  • May 2, 2016: Order 27099 (case 24736)
  • May 2, 2016: Order 27100 (case 24737)
  • Jun 22, 2026: Order 34666 (case 31924), Whiting Oil And Gas Corp.

The units that cover it

A large unit can hold many more wells than its own order allows, because most of them belong to smaller units inside it. Oil totals overlap for the same reason.

1,280 acresPart of sections 2, 3, 10 and 11

Set up
Sep 2013 · Order 22722
Most wells an order allows
1 · 2013
Last real change
Nov 2018
Wells with laterals inside
6
Laterals that still fit
1
Pool
Cartwright-Bakken

1,280 acresPart of sections 3, 4, 9 and 10

Set up
Sep 2013 · Order 22722
Most wells an order allows
1 · 2013
Last real change
Nov 2018
Wells with laterals inside
5
Pool
Hay Creek-Bakken

1,280 acresSections 3 and 10

Set up
Dec 2010 · Order 15467
Most wells an order allows
5 · 2013
Last real change
Jun 2013
Wells with laterals inside
6
Oil reported
773,789 bbl
Pool
Nelson Bridge-Bakken

Wells in the 1,280-acre unit over sections 2, 3, 10 and 11

Horizontal wells with at least 660 ft of lateral inside part of sections 2, 3, 10 and 11, oldest first. Wells of any formation are listed.

Nearby

Sources and limits