Land · Dunn County · T148N R93W

Section 9Township 148 North, Range 93 West

5 spacing units cover this section. The Industrial Commission signed 7 orders on them between 2010 and 2025.

At a glance

T148N R93WNorth ↑ · each square is one section (1 mile)123456789101112131415161718192021222324252627282930313233343536
  • 640-acre unit · section 9
  • 1,280-acre unit · sections 4 and 9
  • 2,546-acre unit · sections 8, 9, 16 and 17
  • 2,560-acre unit · sections 3, 4, 9 and 10
Units overlap. Each was set up by a different order and has its own well allowance. 1 larger unit is listed below.
Spacing units over this section5640 to 3,840 acres
Orders on record72010 to 2025; 7 changed something, 0 restated the rules
Most wells an order allows in the 640-acre unit4in 2011; the latest order read (2018) states 2
Horizontal wells with laterals in that unit77 active; started 2011 to 2023
Laterals that still fit4in 1 of the units; a count of space, not a plan

What happened on this land

The 640-acre unit was set up in 2010, with 1 horizontal well allowed. An order in 2011 raised that to 4. The latest order read, in 2018, states 2; a smaller number usually covers something narrower, not fewer wells for the unit. 7 horizontal wells have laterals in it, started between 2011 and 2023.

123420102015202020251 well4 wellsMost horizontal wells an order has allowedWells started on the unit (one square each)
The 640-acre unit (section 9). The line is the highest well count any order has stated so far: a ceiling, not wells drilled. Start dates are spud dates from the state's wells layer.
  1. 2010
  2. Jan 8, 2010Unit set up

    Set up the 640-acre unit across section 9, with up to 1 horizontal well allowed.

    Order 13965 · Case 11798 · Applicant: Peak ND, LLC

  3. 2011
  4. Jul 18, 2011Pooled

    Pooled the 640-acre unit: the owners' interests across it are combined, and all share in its wells.

    Order 17143 · Case 14867 · Applicant: DAKOTA-3 E&P Co., LLC

  5. Nov 15, 2011More wells allowed

    Raised the 640-acre unit from 1 to 4 horizontal wells allowed.

    Order 18238 · Case 15976 · Applicant: DAKOTA-3 E&P Co., LLC

  6. 2018
  7. Jul 20, 2018Unit set up

    Set up the 1,280-acre unit across sections 4 and 9, with up to 10 horizontal wells allowed.

    States up to 2 horizontal wells for the 640-acre unit; an earlier order stated up to 4.

    Order 28992 · Case 26559 · Applicant: Enerplus Resources (USA) Corp.

  8. 2022
  9. Jun 10, 2022Well count set

    Allowed up to 2 lease-line wells in the 2,546-acre unit, running north–south.

    Allowed up to 1 lease-line well in the 2,560-acre unit, running north–south.

    Restated the rules for the 1,280-acre unit (10 wells).

    Order 31787 · Case 29219 · Applicant: Enerplus Resources (USA) Corporation

  10. 2023
  11. May 12, 2023Well count set

    Allowed up to 1 lease-line well in the 3,840-acre unit, running north–south.

    Restated the rules for the 1,280-acre unit (10 wells).

    Referred to the 2,546-acre unit.

    Restated the rules for the 2,560-acre unit (1 lease-line well).

    Order 32494 · Case 29885 · Applicant: Enerplus Resources (USA) Corporation

  12. 2025
  13. Jul 8, 2025First on record

    First order on record for the 2,560-acre unit across sections 3, 4, 9 and 10.

    First order on record for the 3,840-acre unit across sections 4, 5, 8, 9, 16 and 17.

    Order 34228 · Case 31506 · Applicant: Enerplus Resources (USA) Corp.

The units that cover it

A large unit can hold many more wells than its own order allows, because most of them belong to smaller units inside it. Oil totals overlap for the same reason.

640 acresSection 9

Set up
Jan 2010 · Order 13965
Most wells an order allows
4 · 2011
Latest count read
2 · 2018
Last real change
Jul 2018
Wells with laterals inside
7
Pool
South Fork-Bakken

1,280 acresSections 4 and 9

Set up
Jul 2018 · Order 28992
Most wells an order allows
10 · 2018
Last real change
Jul 2018
Wells with laterals inside
9
Oil reported
2,012,014 bbl
Laterals that still fit
4
Pool
South Fork-Bakken

2,546 acresSections 8, 9, 16 and 17

From the orders only; not in the state's current unit layer.

Lease-line wells
2
Last real change
Jun 2022
Wells with laterals inside
0
Pool
South Fork-Bakken

2,560 acresSections 3, 4, 9 and 10

First order on record
Jul 2025 · Order 34228
Lease-line wells
1
Last real change
Jul 2025
Wells with laterals inside
29
Oil reported
8,065,303 bbl
Pool
South Fork-Bakken

3,840 acresSections 4, 5, 8, 9, 16 and 17

First order on record
Jul 2025 · Order 34228
Lease-line wells
1
Last real change
Jul 2025
Wells with laterals inside
31
Oil reported
8,320,926 bbl
Pool
South Fork-Bakken

Wells in the 640-acre unit

Horizontal wells with at least 660 ft of lateral inside section 9, oldest first. Wells of any formation are listed.

Nearby

Sources and limits

Built November 12, 2026. Find another section · Cases & Orders · Methodology