One spacing unit covers this section. The Industrial Commission signed 5 orders on it between 2008 and 2011, and 2 of those changed something.
At a glance
1,280-acre unit · sections 4 and 9
The outline is the spacing unit that covers this section.
Spacing units over this section11,280 acres
Orders on record52008 to 2011; 2 changed something, 3 restated the rules
Most wells an order allows in the 1,280-acre unit4stated in 2011
Laterals that still fit10in this unit; a count of space, not a plan
What happened on this land
The 1,280-acre unit was set up in 2008. An order in 2011 allowed up to 4 horizontal wells.
The 1,280-acre unit (sections 4 and 9). The line is the highest well count any order has stated so far: a ceiling, not wells drilled. Start dates are spud dates from the state's wells layer.
2008
Mar 26, 2008Unit set up
Set up the 1,280-acre unit across sections 4 and 9.
Order 11691 · Case 9925 · Applicant: Marathon Oil Co.
2011
Mar 18, 2011Well count set
Allowed up to 4 horizontal wells in the 1,280-acre unit.
Order 15865 · Case 13589 · Applicant: Marathon Oil Co.
3 more orders restated the rules without changing them
Nov 21, 2008: Order 12483 (case 10552), Marathon Oil Co.
Read by machine, not checked by a person. Order facts come from the signed orders of the North Dakota Industrial Commission, signed through October 21, 2026. The signed order is the rule.
A record of orders, not title or current status. Nothing here says who owns anything, and a later order can change or end a unit.
Well counts are what each order states. A later order can state a smaller number for something narrower, such as one more well. These pages show the highest count and the latest one read; neither is a statement of what is allowed today.
By section. A unit appears when the orders describe its land by section numbers in one township. Units described by lots or quarter sections may be missing, and a unit smaller than its sections covers only part of them.
Oil is as first reported in the free NDIC Monthly Production Reports, January 2003 to August 2026, for horizontal wells with at least 660 ft of lateral inside a unit, whatever formation they produce from. Overlapping units count the same barrels.
Units and wells come from the state's free GIS layers (spacing units of October 17, 2026, wells of November 1, 2026). A well's status is the Industrial Commission's code, not a judgement.
Not legal, engineering or investment advice. Corrections: see contact.