Land · Dunn County · T143N R94W

Section 35Township 143 North, Range 94 West

One spacing unit covers this section. The Industrial Commission signed 4 orders on it between 2008 and 2010, and 3 of those changed something.

At a glance

T143N R94WNorth ↑ · each square is one section (1 mile)123456789101112131415161718192021222324252627282930313233343536
  • 1,280-acre unit · sections 26 and 35
The outline is the spacing unit that covers this section.
Spacing units over this section11,280 acres
Orders on record42008 to 2010; 3 changed something, 1 restated the rules
Most wells an order allows in the 1,280-acre unit6up from 3 in 2010
Laterals that still fit7in this unit; a count of space, not a plan

What happened on this land

The 1,280-acre unit first appears in the orders in 2008. An order in 2010 allowed up to 3 horizontal wells. An order in 2010 raised that to 6.

24620102015202020253 wells6 wellsMost horizontal wells an order has allowed
The 1,280-acre unit (sections 26 and 35). The line is the highest well count any order has stated so far: a ceiling, not wells drilled. Start dates are spud dates from the state's wells layer.
  1. 2008
  2. Jul 25, 2008First on record

    First order on record for the 1,280-acre unit across sections 26 and 35.

    Order 12018 · Case 10172 · Applicant: Burlington Resources Oil And Gas Co. LP

  3. 2010
  4. May 6, 2010Well count set

    Allowed up to 3 horizontal wells in the 1,280-acre unit.

    Order 14422 · Case 12170 · Applicant: Tracker Resource Development II, LLC

  5. Aug 20, 2010More wells allowed

    Raised the 1,280-acre unit from 3 to 6 horizontal wells allowed.

    Order 15133 · Case 12866 · Applicant: Encore Operating, L.P.

1 more order restated the rules without changing them
  • Jul 27, 2009: Order 13317 (case 11233)

The unit that covers it

1,280 acresSections 26 and 35

First order on record
Jul 2008 · Order 12018
Most wells an order allows
6 · 2010
Last real change
Aug 2010
Wells with laterals inside
0
Laterals that still fit
7
Pool
Murphy Creek-Bakken

Nearby

Sources and limits

Built November 12, 2026. Find another section · Cases & Orders · Methodology